PROJECT / 05

French Fries Processing FacilitySudair, Riyadh, Saudi Arabia

YEAR2025 — Present
STATUSOn Going
AREA40,000 m²
CLIENTAgricultural Growth and Processing Co.
ROLEArchitectural Engineer
DISCIPLINEFactory Building
The completed main processing hall interior with the portal frames receding along the full 15 m span and the finished slab underfoot.FEATURED IMAGE / 05

PROJECT OVERVIEW

From spatial ideato built clarity.

A 15 m high processing facility steel building with 4 floors including Admin, and a separate cold store building 13 m high, plus auxiliary buildings.

SCOPEArchitectureConstructionProject coordinationBIM Technical Documentation

PROJECT DATA

CLIENT
Agricultural Growth and Processing Co.
CONSULTANT
Shahin Engineering
CONTRACTOR
Youssef Marroun Contracting Co.
LOCATION
Sudair, Riyadh, Saudi Arabia
AREA
40,000 m²
CATEGORY
Factory Building
STATUS
On Going
ROLE
Architectural Engineer
HIGHLIGHTS
  • 15 m high steel processing facility over four floors including administration
  • Separate 13 m high cold store building
  • Auxiliary buildings across a 40,000 m² site
  • Full steel erection, formwork and slab reinforcement sequence on site
  • Issued architectural and coordination drawing sheets
The 15 m steel frame erected on site with the first cladding panels fixed to the gable and side elevations.01
Structure / 01PROJECT DOCUMENTATION
Scaffolded timber formwork decks being built between the steel columns under a working platform.02
Construction / 02PROJECT DOCUMENTATION
Scaffolded working platform with the formwork table in place and workers on the deck above.03
Construction / 03PROJECT DOCUMENTATION
Reinforcement grid laid across the slab deck with workers tying bars under the roof structure.04
Construction / 04PROJECT DOCUMENTATION
Close view of the reinforcement mesh across the slab, showing the bar spacing and cover detail.05
Construction / 05PROJECT DOCUMENTATION
Aerial work platform working along the building elevation during the enclosure phase.06
Site / 06PROJECT DOCUMENTATION
The completed main processing hall interior with the portal frames receding along the full 15 m span and the finished slab underfoot.07
Interior / 07PROJECT DOCUMENTATION
Interior view along the length of the hall showing the repeated steel portal frames, roof purlins and the slab below.08
Interior / 08PROJECT DOCUMENTATION
Scissor lift working beneath the metal deck soffit where the structure and first fix are in progress.09
Interior / 09PROJECT DOCUMENTATION
Interior first fix with a scissor lift in place and materials stacked beneath the steel roof structure.10
Interior / 10PROJECT DOCUMENTATION

TECHNICAL DRAWINGS

01 / 03
Drawing / GF-ID-101Ground Floor Zone PlanGround floor zone floor plan, sheet GF-ID-101, colour-coded by zone.